  • SAFEWAY STORE #1771

  • Location: San Jose, CA
  • Quantities: 5,500 sf
  • Job Duration: 3 working days
  • Volume Generated: 72 tons removed for a 98% diversion rate

Scope

  • Emergency response required full mobilization within 12 hours.
  • Selectively remove fallen roof structure back to structurally sound glulam joists that were to remain.
  • Sort through product on 15+ isles that was affected. Source separate damaged goods from salvageable goods, which were then put in crates and placed in the back for inventory.
  • Remove the remaining debris from damaged area and off haul for disposal.
  • Scrape slab and broom sweep clean for next phase of construction.
  • Coordinate with news crews, city officials, PD, and PGE.

SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_2
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_3
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_4
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_5
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_6
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_7
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_8
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_9
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_10
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_2
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_3
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_4
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_5
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_6
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_7
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_8
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_9
SAFEWAY STORE SAN JOSE DEMOLITION PROJECT_10