  • PACIFICA APARTMENTS

  • Location: Pacifica, CA
  • Quantities: 15,000 sf
  • Job Duration: 12 working days
  • Volume Generated: 613 tons removed for a 98.8% diversion rate

Scope

  • Disconnect and safe-off all utilities.
  • Fulfill city and county permit requirements.
  • Coordinate abatement of all hazardous materials prior to demolition.
  • Demolish 15,000 sf of structure, including foundation, down to dirt.
  • Demolish all existing site work, clear and grub.
  • Import 600 cy of engineered fill, backfill, compact, and grade lot +/- 2″.
  • Install HDPE liner 6″ down from final grade to prevent weed growth.

Prevailing Wage/ Performance Bonded