PROJECTS

No matter what, we always get the job done

  • O’CONNER SCHOOL

  • Location: Menlo Park, CA
  • Quantities: 16,500 sf
  • Job Duration: 2.5 working days
  • Volume Generated: 126 tons removed for 98.9% diversion rate

Scope

  • Remove (9) portable classrooms and (3) playgrounds at a school in menlo park that was about to undergo renovation/ expansion.
  • Utility excavation and cut/ cap to all structures prior to demolition commencement.
  • Affluent residential neighborhood required constant dust control with recycled water from our water trucks.
  • Rough grade +/- 6″ upon completion.
  • Worked alongside several other subcontractors in close proximity.
O'CONNER SCHOOL PROJECT_2
O'CONNER SCHOOL PROJECT
O'CONNER SCHOOL PROJECT_3
O'CONNER SCHOOL PROJECT_4
O'CONNER SCHOOL PROJECT_5
O'CONNER SCHOOL PROJECT_6
O'CONNER SCHOOL PROJECT_7
O'CONNER SCHOOL PROJECT_8
O'CONNER SCHOOL PROJECT_2
O'CONNER SCHOOL PROJECT
O'CONNER SCHOOL PROJECT_3
O'CONNER SCHOOL PROJECT_4
O'CONNER SCHOOL PROJECT_5
O'CONNER SCHOOL PROJECT_6
O'CONNER SCHOOL PROJECT_7
O'CONNER SCHOOL PROJECT_8