  • MARINA MARKET

  • Location: San Leandro, CA
  • Quantities: 8,000 sf
  • Job Duration: 1 working day
  • Volume Generated: 156 tons removed for a 98.1% diversion rate

 

Scope

  • Emergency response required full mobilization within 3 hours.
  • Demolish fire damaged structure down to slab and remove debris from roadways.
  • Recover salvageable property inside and submit to San Leandro PD.
  • Use caution around energized upper and lower power lines, 2′-3′ from structure.
  • Coordinate with Fire Department, PD, city officials, news team.
  • Work double shifts, around the clock to finish within 24 hours, minimizing road closure and public hazard.
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT_2
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT_3
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT_4
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT_5
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT_6
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT_8
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT_9
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT_2
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT_3
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT_4
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT_5
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT_6
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT_8
MARINA MARKET SAN LEANDRO DEMOLITION PROJECT_9