  • DISNEY STORE

  • Location: Concord, CA
  • Quantities: 8,800 sf
  • Job Duration: 10 working days
  • Volume Generated: 33 tons removed for a 99.1% diversion rate

Scope

  • Selective interior TI removal at sun valley mall.
  • Remove and dispose of all interior TI build out back to shell.
  • Scrape floor treatments back to slab and grind floors smooth to accept (n) treatments.
  • Cut HVAC back to plenums.
  • Cap water/ utilities back to demising walls.
  • Perform misc. coring in elevated slab to accept (n) utility lines per plan.
  • Coordinate with off hour mall security.
DISNEY STORE DEMOLITION PROJECT CONCORD
DISNEY STORE CONCORD DEMOLITION PROJECT_2
DISNEY STORE CONCORD DEMOLITION PROJECT_3
DISNEY STORE CONCORD DEMOLITION PROJECT_4
DISNEY STORE CONCORD DEMOLITION PROJECT_5
DISNEY STORE CONCORD DEMOLITION PROJECT_6
DISNEY STORE CONCORD DEMOLITION PROJECT_7
DISNEY STORE DEMOLITION PROJECT CONCORD
DISNEY STORE CONCORD DEMOLITION PROJECT_2
DISNEY STORE CONCORD DEMOLITION PROJECT_3
DISNEY STORE CONCORD DEMOLITION PROJECT_4
DISNEY STORE CONCORD DEMOLITION PROJECT_5
DISNEY STORE CONCORD DEMOLITION PROJECT_6
DISNEY STORE CONCORD DEMOLITION PROJECT_7