  • SPRINGHILL SUITES

  • Location: Milpitas, CA
  • Quantities: 40,000 sf
  • Job Duration: 40 working days
  • Volume Generated: 1983 tons removed for a 99.5% diversion rate

Scope

  • Cut 40,000 sf structure in half for adaptive reuse.
  • Demolish (1) 20,000 sf structure, including foundation, down to dirt.
  • Demolish (1) 20,000 sf two story structure back to exterior tilt-up walls.
  • Install tilt up bracing to support load during demolition of 2nd floor and roof.
  • Removal of 48 trees, 600 linear feet of curb and gutter, 1680 cubic yards of concrete.
  • In house fabrication of custom steel shaker plates for long construction entrance.
  • Install and maintain compliance of storm water prevention program, including sediment filters in storm drains, perimeter straw wattle, covering all stockpiles, weed abatement.
  • Rough grade +\- 4″ upon completion.
SPRINGHILL SUITES DEMOLITION PROJECT_2
SPRINGHILL SUITES DEMOLITION PROJECT_3
SPRINGHILL SUITES DEMOLITION PROJECT_4
SPRINGHILL SUITES DEMOLITION PROJECT_5
SPRINGHILL SUITES DEMOLITION PROJECT
SPRINGHILL SUITES DEMOLITION PROJECT_7
DEMOLITION SAFETY
SPRINGHILL SUITES DEMOLITION PROJECT_9
SPRINGHILL SUITES DEMOLITION PROJECT_10
SPRINGHILL SUITES DEMOLITION PROJECT_11
SPRINGHILL SUITES DEMOLITION PROJECT_12
SPRINGHILL SUITES DEMOLITION PROJECT_13
SPRINGHILL SUITES DEMOLITION PROJECT_14
SPRINGHILL SUITES DEMOLITION PROJECT_15
SPRINGHILL SUITES DEMOLITION PROJECT_2
SPRINGHILL SUITES DEMOLITION PROJECT_3
SPRINGHILL SUITES DEMOLITION PROJECT_4
SPRINGHILL SUITES DEMOLITION PROJECT_5
SPRINGHILL SUITES DEMOLITION PROJECT
SPRINGHILL SUITES DEMOLITION PROJECT_7
DEMOLITION SAFETY
SPRINGHILL SUITES DEMOLITION PROJECT_9
SPRINGHILL SUITES DEMOLITION PROJECT_10
SPRINGHILL SUITES DEMOLITION PROJECT_11
SPRINGHILL SUITES DEMOLITION PROJECT_12
SPRINGHILL SUITES DEMOLITION PROJECT_13
SPRINGHILL SUITES DEMOLITION PROJECT_14
SPRINGHILL SUITES DEMOLITION PROJECT_15